SAP Report Painter

Table of Contents

Report Painter

Create Own Layout using Report Painter

Create Planning Layout: KP65

Click Create – Click Lead Column-Select Cost Center- Click Lead column – Select Characteristic Value and Name

Second Lead column – Click New Lead column- Select Cost Element

Total Plan Cost Column : Values are not entered in Lead column. Click the row with Column 1 to create column for entering total plan values

Distribution Key Column

Double click on empty dots- Select attribute – Select Distribution key – Key figure (PWOG) – Update

General Data Selection Column

Edit – Gen Data Selection – Gen data selection – Select version, period, fiscal year

Fix the Decimal place

Place the cursor on Total Plan cost – Click number format

Create Planner Profile

Create Planner profile and assign layout created earlier to it

Transaction : KP34

Select and click General controlling- In Planning area select Cost element and activity input – In currency and Quantity select 1 ( Equal distribution)

Select Planning area and click Layout for controlling – Select layout created in earlier step

Enter Planned values for Cost Center- Cost Elements

Transaction code : KP06

Settings – Set Planner Profile – Select MK11 created in earlier step

Cost Center Report

Transaction code: S_ALR_87013611

Own Layout for Activity Output planning – Report Painter

Transaction Code : KP75

Click lead column – Select cost center – select both Group and Individual – click lead column – Select both characteristic and Name

Second Lead column – New lead – Select activity type – remaining steps same as cost center above

Plan Activity Value

Click on Column 1 – Key figure ( PLST)

Distribution Key column

Double click on dots next to column 1- Select attribute – Distribution key – Key for distribution as PLST

Unit Column

Double click on dots after distribution key – Attribute – Select Unit

Total Plan Price column

Double click on dots after units – Select key figure with characteristic – Key figure is PTOG ( Plan Total Price in object currency)

General Data selection

Edit – Gen Data Selection – Gen data selection – Select Version, Period, Fiscal year– Save

Create Planner Profile

Tcode : KP34

Assign Activity Type planning layout to Planner profile

Use the Planner profile MK11 created earlier and assign layout ACTYPLANMK11 to it

 

Create Activity Type planned values for cost center

Tcode : KP26

Settings – Set Planner Profile- MK11

Explanation

  • Lead Column : These could be Cost Center / Activity Type / Cost Element.
  • Column 1 / Column 2 / Column 3 : These are values for lead column. Like Plan activity value, Plan activity Units (HR), Plan activity Distribution type (1- Equal, 2- Monthly etc.), Plan total Price
  • General Data Selection: Here you specify the header values- Version, Period, Fiscal Year

Report Painter for SKF Planning

Transaction code: KP85

Assign to Planner Profile: KP34

  1. Cost Center Reposting, Allocation, Assessment

Please visit next tutorial on Product Costing Business Process, Configuration and Testing in SAP

1 thought on “SAP Report Painter”

  1. Pingback: Course Material - AIERP2

Leave a Comment

Your email address will not be published. Required fields are marked *

error: Content is protected !!