Table of Contents
Product Costing Concepts
- Find Cost which are part of Product Cost (COGM)
- Find optimum Lot size for manufacturing the product
- Find Product cost for each manufacturing location / Plant
- In Product costing we estimate the product cost. Product cost estimate is also known as standard product cost
- Various techniques used to calculate product cost estimate are as below:
- BPO: Base Planning Object
- Cost Estimate without quantity structure
- Cost estimate with Quantity Structure: BOM and Routing
- BOM: It is list of Raw material along with their quantity used to manufacture the product
- Routing: List of activities like operation 1, operation 2 etc. performed on raw material to convert it into finished goods
- Product Costing is divided into 3 different topics as below:
- Planning: Calculate standard cost
- Cost Object Planning: This will cover period end process, i.e. Planned cost, Actual cost, variance, settle production order
- Actual Costing / Multiple valuations: Material Ledger
Standard cost estimates settings- Concept
Tcode: CK11N
Cost Component Split | Material Cost Labor Cost Machine Cost Setup Cost Mat OH Admin OH | All these together make COGM (Cost of goods manufactured) |
Costing Variant | Made of be below components | |
Costing Type | Determine cost type like Standard cost | |
Valuation Variant | ||
Material | ||
Activity | ||
Subcontract | ||
External | ||
OH -Costing Sheet | ||
Date Control | Validity period of standard cost estimate | |
Qty. Structure control | BOM + Routing = Qty Structure Qty structure control determine which BOM and Routing is used for standard cost estimate | |
Transfer Control | Standard cost is calculated per plant. Transfer control used to see if same standard cost can be used for other plants | |
Ref. Variant | ||
Integration with PP (Production Planning) |
Product Costing Types – Concept
There are two Product Costing Types
- MTS (Make to Stock): In this type goods are produced and stocked. They are sold from the stock. Under MTS there are two scenarios
- Product Costing by order
- Product costing by period
- MTO (Make to Order): This is used for large equipment’s, aircraft manufacturing etc. In this type manufacturing of product starts after receiving the sales order.
Cost Object Controlling – Settings
This involves settings for below activities
- Costing variant for Plan cost
- Costing variant for Actual Cost
- Period end process:
- WIP
- Variance (Plan – Actual Cost)
- Settlement: This involve settlement of production order
- Create PA transfer structure for COPA
- FI entries for WIP and variance are posted only at the time of production order settlement
Integration with PP (Production Planning)
Costing Sheet Configuration
Costing Sheet explanation
What is Costing sheet:
The costing sheet integrates all elements of overhead costing. It consists of the following rows that are processed during the calculation:
- Base Row: This contain the calculation Base. Calculation base is made up of cost elements on which OH is calculated
- OH Rates Row: This contain OH Rates. OH rates contain percentage rate which applied on calculation base to arrive at OH amount
- Total Rows: Used to form subtotal or total of earlier rows. No calculation performed on these rows
Step | Base | OH Rate | Description | From | To | Credit |
1 | 19MC | Material Cost | ||||
2 | 19AC | Activity Cost | ||||
3 | 19MH | Material OH | 1 | 1 | 19M | |
4 | 19AH | Activity OH | 2 | 2 | 19A | |
5 | 1 | 4 | ||||
6 | ||||||
19MC: Material Cost: Raw Material Cost (CE from 400000 to 400001) | ||||||
19AC: Activity Cost: Machine Cost, Labor cost, Cleaning (CE from 943000 to 943002) | ||||||
19mh Dep Key is D020 Plant (OH Calculation based on %) | ||||||
Valid Fr | Valid To | CO Area | OH Type | Plant | Percentage | |
1042018 | 31129999 | MK14 | 1 | 01M1 | 10 | |
1042018 | 31129999 | MK14 | 2 | 01M1 | 10 | |
1042018 | 31129999 | MK14 | 1 | 01M1 | 10 | |
1042018 | 31129999 | MK14 | 2 | 01M1 | 10 | |
19ah Dep Key is D020 Plant (OH Calculation based on %) | ||||||
Valid Fr | Valid To | CO Area | OH Type | Plant | Percentage | |
1042018 | 31129999 | MK14 | 1 | 01M1 | 15 | |
1042018 | 31129999 | MK14 | 2 | 01M1 | 15 | |
1042018 | 31129999 | MK14 | 1 | 01M1 | 15 | |
1042018 | 31129999 | MK14 | 2 | 01M1 | 15 | |
Credits: Determine which cost center is credited using which credit element | ||||||
CE | CCTR | |||||
19M | 941000 | 3319005 | Cost center 3319005 is credit using CE 941000 | |||
19A | 941001 | 3319005 |
Set Controlling Area: OKKS
Controlling area: MK14
Define Costing Sheet Components- Calculation base
Path: SPRO – Controlling – Product Cost Controlling – Product Cost Planning – Basic settings for material costing – Overhead – Costing sheet components – Define Calculation base
The calculation base determines to which cost elements overhead is applied together.
Define Costing Sheet Components- % OH Rates
Path: SPRO – Controlling – Product Cost Controlling – Product Cost Planning – Basic settings for material costing – Overhead – Costing sheet components – Define Percentage OH rates
Define percentage overhead rates, for example, 10% in controlling area AUM1.
Select OH Rate 19MH and below entries
Select 19AH OH rate and make the below entries
Define Costing Sheet Components- Credits
Path: SPRO – Controlling – Product Cost Controlling – Product Cost Planning – Basic settings for material costing – Overhead – Costing sheet components – Define Credits
Here you define Cost center which is to be credited with OH cost. Further this credit is recorded under secondary cost element of category 41 (overhead rates)
Define Costing Sheet
Path: SPRO – Controlling – Product Cost Controlling – Product Cost Planning – Basic settings for material costing – Overhead – Costing sheet
Select Base, OH or Credit and click the respective row to see the details configured earlier
Define Costing Variant
Costing Variant contain Costing Type, Valuation Variant, Date Control, Quantity structure control, Transfer control and reference variant. We will create three costing variants – Standard cost, Planning cost and Actual cost variant
Costing variants is the link between product costing and Customizing,
The costing variant contains all the control parameters for costing.
The costing variant for a material cost estimate contains the following control parameters:
- Costing type
- Valuation variant
- Date control
- Quantity structure control
- (only relevant for cost estimates with quantity structure)
- Transfer control (optional)
- Reference variant (optional)
Costing Variant (Contain Costing Type, Valuation Variant) | ||||||
Costing Type Determine | ||||||
Standard Costing | Other than Standard costing | Costing for reporting | Quotation | |||
Valuation Variant determine | ||||||
Material Valuation (Material can have many prices in MM03. Price sequence have to defined here) | Activities Valuation (Can have many price. Priority sequence to be defined) | Subcontract (For e.g. a Semi FG purchased from a vendor). Price sequence to be defined here | External Operations (Operation outsourced to a vendor). Price sequence to b e defined | Over heads | ||
Mov Avg Price | Avg price for 12 months | PO Price | Price for operation | Costing sheet defined earlier | ||
Standard Price | Current period price | Purchase Info Record price | Purchase order price | |||
Pur Info Record Price | Previous period price | Purchase infor record | ||||
Date Control | Costing Date from | Current Date | ||||
Costing date To | Maximum Date | |||||
Qty structure date | Current Date | |||||
Valuation Date | Current Date | |||||
Quantity structure control | ||||||
BOM Application Area | ||||||
Routing selection ID | Task List Type | N (Product Cost By Order) | ||||
R | ||||||
2 (Product cost by process order) | ||||||
Transfer Control | Single Plant | Cross Plant | ||||
Ref Variant | Optional |
Note:
Costing Type: Determine type of cost is calculated., whether standard cost, Cost for reporting, etc.
Valuation variant determine how Material, Activities, Subcontract, External Operations and OH are valued
Date Control: Determine validity period of costing run
Product Costing Training-Advance
Define Costing Variant-Costing Type
Path: Controlling – Product Cost controlling – Product Cost planning – Material Cost estimate with quantity structure – Costing variant components – Define costing type
Here you define the purpose of a material cost estimate by specifying, field in the material master record to which the costing results can be transferred to:
Update – Material master Fields | Cost Estimate (CK40N) |
Standard price | Standard cost estimate (01) |
Tax-based price | Inventory cost estimate |
Commercial price | Inventory cost estimate |
Price other than std price | Modified standard cost estimate |
In a client there can be only one costing type for standard price. We will keep SAP standard costing type 01 for standard price
Define Valuation Variant
Path: Controlling – Product Cost controlling – Product Cost planning – Material Cost estimate with quantity structure – Costing variant components
Here you specify parameters to be used for cost estimate
- Material Valuation: define the sequence in which the system searches for prices from the accounting view or costing view of the material master record to valuate materials. E.g. We can specify the sequence in which material price is picked – use moving average price, if not available use Standard Price, if not available use Purchase Info record and so on
- Activity Price: Sequence in which activity price is picked. For e.g. take Plan activity price, if not available take actual activity price and so on
- Overhead costs: Link the costing sheet prepared in earlier steps to pick the OH cost for cost estimates
Activity type price priority
Sub-contracting price sequence
External Operations price sequence
Under OH select the costing sheet created earlier
OH, on Material Components. Not required in our scenario. If costing sheet assigned here OH 10% and 15% defined in costing sheet will be added to the raw material
To display Number in the drop down enable visualization in the options as below
Valuation variant is defined at plant level
Click and assign Valuation variant A6 to our plant 01M1
Define Date Control
Path: Controlling – Product Cost controlling – Product Cost planning – Material Cost estimate with quantity structure – Costing variant components
Tcode: OKK6
Date control determines which dates are proposed or displayed when a cost estimate is created, and whether these dates can be changed by the user.
- The validity period of the cost estimate
- The date on which the quantity structure is determined ( quantity structure date)
- The date on which the quantity structure is valuated ( valuation date)
Define Quantity Structure Control
Path: Controlling – Product Cost controlling – Product Cost planning – Material Cost estimate with quantity structure – Costing variant components
Tcode: OKK5
Check BOM Selection
Path: Controlling – Product Cost controlling – Product Cost planning – Material Cost estimate with quantity structure – Settings for qty structure – BOM Selection – Check BOM selection
Tcode: OPJI
BOM: BOM (Bill of Material): This is list of Raw material along with the quantities required to produce Finished Goods
Specify different sequences of priorities of BOM usages according to your requirements
Path: Controlling – Product Cost controlling – Product Cost planning – Material Cost estimate with quantity structure – Settings for qty structure – BOM Selection – Check BOM application
Tcode: OPJM
Here you define BOM application area. Now you assign BOM selection ID created earlier to this BOM application area. Selection ID decides the sequence in which BOM are selected during cost estimate for this BOM application area
Check Routing Selection
Path: Controlling – Product Cost controlling – Product Cost planning – Material Cost estimate with quantity structure – Settings for qty structure – Routing Selection – Check automatic routing selection
Tcode: OPJF
Routing: It is sequence of activities. It specifies on which Work Center (A work center typically refers to a machine) what activities are to be performed for how many hours. Raw Material is converted into finished goods at work center
Define a Routing selection ID
Assign it to alternative selection priorities
Specify selection priority for each of these scenarios
- ID: A6: Can be any identifier
- SP: Selection Priority
- Task List: N: Routing, R: Rate Routing
- Plan Usage: 1: Production
- Status: 4: Released general
Assign BOM application ID and routing selection ID in Quantity structure control
Tcode: OKK5
PP01 replaced with A6
Define Transfer Control
Path: Controlling – Product Cost controlling – Product Cost planning – Material Cost estimate with quantity structure – costing variant component – define transfer control
Tcode: OKKM
Transfer Control: The transfer control specifies how the existing cost estimate is to be used in the cost estimate of the other product. For e.g. Costing done at beginning of the year. All components of the product cost have to be costed to arrive at final Standard Cost. Costing of new component during the year. We can use standard cost of components costed at the beginning of the year if they are being used in manufacture of this new Product. Here we will use the transfer control
In this step you define parameters for partial costing. The purpose of partial costing is to prevent the system from creating a new cost estimate for a material when costing data already exists. Instead, the existing costing data is simply transferred into the new cost estimate. This improves performance.
Current and Future cost kept for 6 months before archiving
Define Costing Variant
Path: Controlling – Product Cost controlling – Product Cost planning – Material Cost estimate with quantity structure – Define costing variant
Tcode: OKKN
Select costing component created in earlier steps and assign to Costing variant MK14. Costing type assigned is 01 Standard Cost and not one created earlier as we want to do standard costing
Qty Structure selection
Additive cost. These are transportation, packing cost added to COGM.
Update selection
Itemization: Detailed break up of cost based on its components
Error management selection
Assignment are optional so ignored for now
Define Cost Component Structure
Path: Controlling – Product Cost controlling – Product Cost planning – Basic settings for material costing – Define Cost component structure
Tcode: OKTZ
It gives the breakup of the cost estimate of products like material cost, packing mat cost, consumables, Mach. Cost etc. The cost component structure contains the cost components (grouping of costs or cost elements)
Each cost component specifies whether it is relevant for valuation of inventory or not and also it specifies under which cost components to be updated. E.g.. COGM, COGS, Inventory, and Tax inventory etc. Each cost component specifies whether it is to be rolled up or not.
Any component which is relevant for inventory should be rolled up and shown under COGM view.
The cost component can have maximum of 40 components in case of all components are variable. In case of all components are fixed, then the CCS can have maximum of 20 components.
Cost Component Structure: Break up of component cost | |||||||
Cost Component Group (CCG): Group of cost components | Views | ||||||
FC / VC: Fixed / Variable Cost | |||||||
Cost Component | Cost Element | CCG | FC/ VC | COGM | Inv Val | Comm Inv | Tax Inv |
Material Cost | 400000-400,001 | 9M | VC | Y | Y | Y | Y |
Packing Cost | VC | Y | Y | Y | Y | ||
Consumables | VC | Y | Y | Y | Y | ||
Set up Activity cost | 943000 | 9D (Direct OH) | FC & VC | Y | Y | ||
Machine Activity cost | 943001 | FC & VC | Y | Y | |||
Labor activity cost | 943002 | FC & VC | Y | Y | |||
Material OH | 941000 | 9I (Indirect OH) | VC | Y | Y | Y | Y |
Activity OH | 941001 | FC & VC | Y | Y |
Define cost component Group (CCG)
Path: Controlling – Product Cost controlling – Product Cost planning – Basic settings for material costing – Define Cost component structure
Tcode: OKTZ
Define Cost Component Structure
Define Cost Component with attributes
Select CCS B1 and double click Cost component with attributes. Define as below:
Cost displayed in CCG 9M in cost break up
Packing Cost component
Consumables cost component
Setup Activity Cost
Machine Activity Cost
Labor Activity Cost
Material OH
Activity OH Cost Component
Assign Cost Components to Cost Elements
Select the views for this cost component structure
COGM: Select COGM
COGS: Cost of goods sold = COGM + Selling and Admin cost
Inventory commercial view = COGM + Inventory commercial
Inventory valuation
Assign Cost component structure to Organizational Units (Co Code and Plant)
Activate Cost Component structure
Activate CCS to Controlling area currency
Path: Controlling – Product Cost controlling – Product Cost planning – Select functions in material costing – activate CCS in CO Area currency
Difference between Plan Cost, Standard Cost and Actual Cost
Plant Cost | Standard Cost | Actual Cost |
Plan cost for a job order | Estimated cost per unit | Actual cost |
Difference between plan cost and actual cost is of Fixed Cost. Fixed cost does not change in plan cost
Define Costing variant for Plan
Tcode: OPL1
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – manufacturing orders- Check costing variant for manufacturing orders – new entries
We will use Valuation variant A6 created earlier
Costing Type we will use SAP standard: 06 Planned Production Order
Define Costing variant for Actual
Tcode: OPL1
Create Product Cost Collector
Create / Check Order Types
Path: Controlling – Product Cost Controlling – Cost Object Controlling – Product Cost by Period – Product Cost Collector
Default values for Order cost estimate
Create Product Cost Collector: KKF6N
Select Product Cost Collector in Production Order type and Plant default values
Path: Controlling – Product Cost Controlling – Cost Object Controlling – Product Cost by Order – Manufacturing Orders
Product Costing Period End Process and WIP
Mth 1 | Mth 2 | Mth 3 | Std Cost | ||
Standard Cost | 1 Kg (Std Cots is per 1 Kg) | 10000 | |||
Production Order | 10 Kg | 6 Kg | 4 kg | ||
Release | Partial DLV | Full DLV | TECO | Close | |
1st Month Cost (Rmatl, OH, Activity Cost) | 20000 | 20000 | 20000 | 20000 | |
2nd Month Cost | 70000 | 70000 | 70000 | ||
3rd Month Cost | 30000 | 30000 | |||
OH Cost (Can be added to Order even at TECO) | 10000 | ||||
GR (6 kg Goods received by inventory) | -60000 | -100000 | -100000 | ||
Period End Process | |||||
Order Balance at ME | 20000 | 30000 | 20000 | 30000 | |
WIP ( Equal to Order Balance) | 20000 | 30000 | Nil ( Order fully delivered) | 0 | |
Variance (Cal only at FULL DLV, TECHO) | NA | NA | 20000 | 10000 | |
Settlement (Production Order cost transferred from CO to FI GL Accounts) | |||||
FI Acct Entries | |||||
WIP Material (B/S) DR | 20000 | 10000 | |||
WIP P/L CR | 20000 | 10000 | |||
Full DLV – WIP is zero, so above entries reversed at settlement | |||||
WIP P/L DR | 30000 | ||||
WIP Material (B/S) CR | 30000 | ||||
Balance is removed from Production order through variance posting | |||||
Production Variance DR | 20000 | 10000 | |||
To COGM CR | 20000 | 10000 | |||
CO Document Posting – FULL DLV- Settlement | Prod Order – CR (20000 for variance) | 10000 |
WIP Settings
- Define RA Key
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress – Define RA Key
Tcode: OKG1
- Define CE for WIP calculation
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress
Create below secondary (31 category CE): KA06
Sec CE | Name | CE Category |
931000 | WIP Material Cost | 31: Prod Order/ Project Result |
931001 | WIP Direct OH | 31: Prod Order/ Project Result |
931002 | WIP Indirect OH | 31: Prod Order/ Project Result |
931003 | WIP Technical (Total of all WIP) | 31: Prod Order/ Project Result |
- Define RA version
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress
All results analysis data calculated in results analysis is updated on the order with reference to the results analysis version. This enables you to calculate work in process on the basis of multiple results analysis versions. This means that you can use different results analysis versions to define different methods of WIP calculation
Click Extend control ON
Save and deselect Transfer to Financial Accounting. This will be reselected after completing subsequent steps
- Define valuation methods actual
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress
- In this step you define a valuation method for the calculation of work in process.
- In the Product Cost by Period component the work in process is valuated at target costs. The valuation is made based on the quantities confirmed at the operations point
- In the Product Cost by Order component the work in process is normally valuated at actual costs. The value of the work in process is the difference between the debit and the credit of an order if the order has the status PREL (partially released) or REL (released).
- Define Line ID
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress
Define Line ID. In next step you assign CE to these Line ID. Line ID receive WIP value from these CE at the time of Production Order Settlement. Create a Secondary CE of category 31 and assign to these Line ID. Secondary CE receive the settled cost. Secondary CE is mapped to FI BS and PL account. This enable posting of FI documents for WIP balance at the time of production Order settlement
Line ID show WIP breakup. New entries and below entries
- Define Assignment
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress
Assign CE / GL accounts to WIP line ID’s created in above step
SAP GL account length is 10 digits. When masking prefix zeroes if length less than 10 digit
- Define Update
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress
Tcode: OKGA
- Define Posting Rule for settling WIP
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress
Tcode: OKGA
Create below GL accounts: FS00
GL Acct | Description | Type | Account Group | FSG | Line Item | Sort key |
200126 | WIP Mat Cost BS | BS | Current Assets | G006 | X | 001 |
200127 | WIP DOH Cost BS | BS | Current Assets | G006 | X | 001 |
200128 | WIP IOH Cost BS | BS | Current Assets | G006 | X | 001 |
400205 | WIP Mat Cost PL | PL | Manufacturing Expenses | G001 | X | 001 |
400206 | WIP DOH Cost PL | PL | Manufacturing Expenses | G001 | X | 001 |
400207 | WIP IOH Cost PL | PL | Manufacturing Expenses | G001 | X | 001 |
MTS: Make to Stock use WIPR
MTO: Make to Order use RUCR
Secondary CE 931000 post WIP material cost to BS:200126 and PL 400205 account
Define Number Ranges
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress
Click Groups and assign element KABG and KABM to MK14 secondary group
Select Transfer to FI in RA version
Path: Controlling- Product Cost Planning – Cost Object Controlling – Product Cost by order – Period end closing – work in progress
Variance Calculations
Variance Calculation determines differences between the actual costs incurred on a production order and the standard costs of the material produced. Variances are calculated not at once, but for different variance categories.
Define Variance Keys
Path: Controlling – Product Cost Controlling – Cost Object Controlling – Product Cost by Order – Period End Closing – Variance Calculation
Tcode: OKV1
Variance key is added to Finished Goods material Master. From the material master it is transferred to production order and control variance calculation
Define default variance keys for plants
Path: Controlling – Product Cost Controlling – Cost Object Controlling – Product Cost by Order – Period End Closing – Variance Calculation
Tcode: OKVW
Define variance variant
Path: Controlling – Product Cost Controlling – Cost Object Controlling – Product Cost by Order – Period End Closing – Variance Calculation
Tcode: OKVG
Define target cost version
Path: Controlling – Product Cost Controlling – Cost Object Controlling – Product Cost by Order – Period End Closing – Variance Calculation
Tcode: OKV6
Variance Formula = Control Cost – Target cost
Now Control cost can be Actual Cost or Plan cost depending on version
Target cost can be current standard cost or any other cost depending on version
Define Controlling area version for Plan
Tcode: OKEQ
Select and Click controlling area settings
Select and click settings for each Fiscal Year
Similarly create version A8
Now create Target cost version for A7 and A8
Version A7
Version A8
Define Number Range for Variance Documents
Path: Controlling – Product Cost Controlling – Cost Object Controlling – Product Cost by Order – Period End Closing – Variance Calculation
Tcode: KANK
Business Transaction : KVAR : assign to secondary postings
Settlement
Create Settlement Profile
Path: Controlling – Product Cost Controlling – Cost Object Controlling – Product Cost by Order – Period End Closing- Settlement
Settlement profile used for settlement of Production order
To be Settled in Full: Production order can be settled only when balance is zero
Can Be settled: Order can be settled even with the balance
Not for settlement: WIP can be settled. Variances cannot be settled
Max no. Dst rls: Maximum 6 receiver allowed in settlement profile
Residence time: 6 months before it is archived
Maintain Number Range for Settlement Documents
Path: Controlling – Product Cost Controlling – Cost Object Controlling – Product Cost by Order – Period End Closing- Settlement
Tcode: SNUM
Create Group
Click Change group
Click create and create below group
Search MK14 (settlement profile created in last step) and assign to the group
Master SAP Product Costing Course
For Detailed step by step instruction on SAP Cost Center Accounting, Product Costing, Profit Center Accounting, Internal Orders configuration, testing follow my video tutorial below
Please visit next tutorial on Product Costing in SAP tutorial 2